Example building company
Progress Report · Report 6Kōwhai House
Progress Report · Report 6
Kōwhai House
Example address, Wellington
- Report date
- 13 Nov 2026
- Reporting period
- 9 to 13 Nov
- Prepared by
- Mara
- Prepared for
- Alex & Sam
- Report number
- 6
Project update
North elevation weatherboards are installed and the deck landing is built to drawing A-104 Rev C. The roofer starts Monday and the services rough-in carries on, subject to the agreed programme. Two decisions are needed from you next week: the exterior colour and the finish change.
Completed items
- North elevation weatherboards installed.Completed 11 Nov 2026
- Deck landing built, following A-104 Rev C and instruction SI-014.Completed 12 Nov 2026
- Roof framing checked with the roofer ahead of Monday’s start.Completed 13 Nov 2026
Work in progress
- Weatherboards to the east and west elevations.Carpenter
- Electrical and plumbing rough-in.Electrician, plumber



