Site diary

Kōwhai House

12 November 2026 · Example building company
Example
Edit the notes and save an example diary entry.

Today’s entry

Demo only

The connected project record

Fictional scenario across 10 to 20 November 2026. All amounts below are NZD excluding GST unless stated. No retention or other adjustments are modelled.

  1. SI-014 · 10 November · additional deck landing instructed to A-104 Rev C.
  2. DW-022 · 12 November · 16 hours × $85 + $540 timber + $180 fixings = $2,080.
  3. VAR-007 · 13 November · direct cost + $208 markup (10%) = $2,288, approved by Alex & Sam.
  4. PC-003 · 20 November · $42,000 base work + $2,288 approved variation = $44,288. GST $6,643.20; including GST $50,931.20.
Original contract
$480,000
Revised contract
$482,288
Earlier claims
$120,000
Claimed to date
$164,288